Key steps in the EES process

Over the past two years, we’ve been working on the technical studies needed for planning approvals, including the preparation of an Environment Effects Statement (EES).

An EES is Victoria’s most stringent and transparent impact assessment process. It gives decision makers such as the Minister for Planning and the Environment Protection Authority (EPA) Victoria, the information they need to determine whether planning approvals should be granted and what conditions should apply.

Next steps in the EES process

The revised Planning Scheme Amendment (GC98) was approved by the Minister for Planning on 23 December 2019 and gazetted on 3 January 2020. A copy is available on the Department of Environment, Land, Water and Planning website here. The Environmental Performance Requirements the project will need to meet during planning, construction and operation will be reviewed and approved by the Minister for Planning in the coming months as part of an Environmental Management Framework. EPA Victoria is expected to make a decision on the Works Approval Application for the construction and the operation of the tunnel ventilation structures soon.

In addition to receiving planning approval in Victoria through the EES process, the project received approval from the Commonwealth Government in December 2019 under the Environment Protection and Biodiversity Conservation Act. More information about the Commonwealth approval process is available here.

Separate to the EES process, The Cultural Heritage Management Plan (CHMP) is expected to be approved by the Wurundjeri and Aboriginal Victoria in the next few weeks.

2020 - Early works for North East Link are expected to start in early 2020.

2021 - Construction for North East Link is expected to start by 2021.

2027 - North East Link is expected to open to traffic in 2027.

Previous

Early 2018 – North East Link referred the project to the Minister for Planning. Read the project outline here.

2 February 2018 – Minister decided that an EES is required. Read the declaration here.

22 May 2018 – Minister issued draft Scoping Requirements for public comment.

24 June 2018 – Minister issued final Scoping Requirements. Read the Scoping Requirements here.

Wednesday 10 April 2019 – The EES went on display for 40 days and was open for public submissions

Friday 7 June 2019 – EES submissions closed at 5 pm

Friday 21 June 2019 – Directions Hearing held to make arrangements for and answer questions about the Public Hearing

Mid 2019 – The Minister for Planning appointed an independent Inquiry and Advisory Committee (IAC) panel to review the EES and public submissions received and make recommendations.

July - September 2019 – The thirty four day public hearing commenced Thursday 25 July and concluded Monday 16 September.

September - October 2019 – After the public hearings the independent Inquiry and Advisory Committee (IAC) prepared a report of recommendations and submitted it to the Minister for Planning. The report was provided to the Minister within 30 business days of the completion of the public hearing.

5 December 2019 – The Minister for Planning released IAC’s report including their recommendations together with his assessment on the environmental effects of the project. The Minister’s assessment considered the committee’s recommendations as well as the information presented in the EES, public submissions and evidence presented during the public hearings, and ultimately concluded that the environmental effects could be satisfactorily managed.

December 2019 – North East Link reviewed the assessment in detail and submitted a revised Planning Scheme Amendment to the Minister for Planning.